The Spreadsheet That Wanted to Be a System
Most project control stories begin with a mess: a folder of disconnected spreadsheets, a pipeline tracked in one file and delivery in another, and a finance team that learns the true margin only when the project closes. Dr. Jürgen Fleig, writing for the Management-Handbuch published by business-wissen.de, took a different approach. He did not propose a methodology. He shipped a product – a numbered catalog of Excel templates, each with an article number and a file extension, designed to lock together into a single control loop.
The promise is pragmatic: rigorous project control without the cost or complexity of enterprise Project Portfolio Management (PPM) software. The mechanism is familiar: master data, pivot tables, and VBA macros. The innovation lies in how the pieces connect – or where they deliberately do not.
Anatomy of the Control Loop
Master Data as Dimensional Scaffolding
Before a single offer is entered, the system demands three lists: Departments, Cost Centers, and Customers. This is not administrative theater. These dimensions become the axes of every pivot report that follows. By fixing them early, the template transforms a project tracker into a controlling instrument capable of attributing profit and loss to organizational units. A sales director can filter by cost center; a controller can slice by customer. The structure forces the discipline that ad-hoc spreadsheets never do.
The Offer-to-Project Gateway
The workflow hinge is a status machine. Offers move through defined states – in Arbeit, abgegeben, in Verhandlung, hängend, erteilt/abgelehnt. Only when status flips to erteilt (awarded) does the offer spawn a project entity. At that moment, two numbers lock in: the Order Sum (Auftragssumme) and the Planned Costs (Plankosten).
The derivation is deliberate: Planned Costs = Order Sum minus Profit Markup. This is top-down budgeting. The margin is fixed at the sales stage; the delivery team inherits a cost ceiling. The system also captures the delta between Offer Sum and Order Sum, turning negotiation discounts into a visible controlling metric rather than a buried contract detail.
The Running Calculation: Dual-Track Variance
The core artifact is the mitlaufende Kalkulation – a running calculation that tracks two variances in parallel:
- Schedule Variance: Planned End Date versus Estimated or Actual End Date, measured in days.
- Cost Variance: Planned Costs versus Estimated or Actual Costs.
Here lies the system’s most consequential design choice. Actual and Estimated Costs are not calculated from individual employee rates multiplied by hours. Instead, the formula is: Employee time records × Average Hourly Rate.
This blended-rate approach eliminates the need for per-employee rate cards, escalation logic, or rate maintenance. It drastically reduces master-data overhead. But it introduces a systematic distortion: a project staffed by senior architects looks equally expensive as one staffed by juniors if the hours are equal. The model cannot distinguish between rate variance and efficiency variance. For professional services firms where resource mix is the product, this abstraction decouples the control signal from resource reality.
The Four-Metric Dashboard
Fleig codifies four KPIs that structure the review cadence:
- Hit-Rate (Auftragsquote): Successful Offers divided by Total Offers, filterable by Team or Customer. A leading indicator for pipeline health.
- Time Variance (Terminabweichung): Days delta. A leading and lagging indicator for delivery risk.
- Cost Variance (Kostenabweichung): Currency delta. The primary margin protection signal.
- Profit Variance (Gewinnabweichung): Planned Project Surplus versus Actual Surplus. The bottom-line synthesis metric.
The instrumentation for early warning exists. The organizational response mechanism – who acts, when, and how – is assumed.
The Template Ecosystem as Architecture
The chapter functions as a bill of materials. The versioning strategy reveals the installation-base reality:
- Core Engine (Art. 99.146.01): Angebotsverfolgung, Projektsteuerung und Projektabrechnung – a macro-enabled .xlsm file containing the offer pipeline, project control logic, and invoicing module with support for up to six partial invoices per project.
- Input Layer – Time Recording: Two macro-free .xlsx variants: nach Wochentag (by weekday) and fortlaufend (continuous). The absence of VBA is deliberate: timesheets are the highest-volume, widest-audience artifact. Removing macros lowers the barrier to entry and avoids macro-blocking policies.
- Analytics Layer (cross-reference Chapter 120): Five specialized controlling add-ons for cost controlling, cost trend analysis, time-cost trend charts, effort planning, and project task calendars.
- Visualization: A Burndown Chart template (Art. 99.143.10) for graphical budget burn.
Compatibility notes are explicit: the core engine targets Excel 2013; the macro-free input files and analytics add-ons were built for Excel 2016 and newer but remain usable back to Excel 2010, with the caveat that minor display errors cannot be ruled out in older versions.
Where the Model Meets Reality
The Discount Leakage Lens
A sales manager filters the Offer Tracking pivot by customer and status erteilt. The pivot reveals the aggregate delta between Offer Sum and Order Sum across the portfolio. Without this template, that leakage lives in individual PDF contracts. The controller uses the actual Order Sum to set the Planned Cost baseline for the resulting projects, ensuring the running calculation starts from contracted revenue, not list price.
The Blended-Rate Blind Spot
A project carries a Planned Cost derived from the awarded order value minus markup. The team logs hours in the macro-free timesheet. The system applies the company Average Hourly Rate. The variance flag triggers. But the project manager knows the hours comprise a heavy senior mix. The true cost – calculated at market rates per role – exceeds the blended-rate actual by a material margin. The system understates the overrun. The corrective action it prompts (reduce hours) addresses the symptom in the model, not the root cause (staffing mix).
The Six-Invoice Ceiling
A fixed-price project uses the Zahlungsmanagement table. The payment schedule fits within six milestones. Then a change order adds two partial invoices, and a penalty deduction requires a credit-note pair. The template hits its hard structural limit: six invoice columns, fixed in the schema. The workaround – duplicating the project row or maintaining a shadow ledger – breaks the single-source-of-truth promise.
The Macro Blockade
An engineering firm rolls out the core .xlsm. Group Policy blocks unsigned macros. The ribbon customizations and event handlers (Workbook_Open, Sheet_Change) that drive status transitions and pivot refreshes fail to load. The firm cannot sign the VBA project internally. They fall back to the macro-free variants and eventually re-engineer the logic in Power Query – a hidden Total Cost of Ownership not reflected in the handbook price.
Structural Fault Lines
File-Based Concurrency
The system is fundamentally single-user or sequential-multi-user (check-in/check-out via file server, SharePoint, or Teams). No record locking, no merge logic. Simultaneous editing by a project manager updating status and a controller refreshing pivots risks data corruption or last-save-wins losses. This limits the practical team size to a handful of active editors per workbook instance.
Hard-Coded Ceilings
The six-invoice limit is a schema constraint – likely fixed columns. Extending it requires unprotecting sheets and modifying VBA, voiding the template guarantee. Similarly, the status fields (five states for offers, five for projects) are validation lists that require sheet unprotection to modify. The system resists adaptation.
VBA Dependency Surface
The core value proposition – automation, ribbon, event-driven logic – lives in the macro-enabled workbook. The macro-free timesheets are input-only. Organizations with strict no-macro policies lose the control engine entirely.
German Regulatory Coupling
Terminology (Kostenstelle, Auftragssumme, Mitlaufende Kalkulation, Abnahme, Vorfinanzierung) and logic assume a German Handelsgesetzbuch / GoBD context. Transfer to US GAAP or IFRS environments requires semantic translation: Cost Center does not map cleanly to Profit Center; Abnahme implies formal acceptance protocols not universal in Agile or US contract practice.
The Migration Accelerator Frame
Fleig’s system is best understood not as a project control methodology but as a Legacy Migration Accelerator. It professionalizes chaotic Excel sprawl today while building the data discipline – master data hygiene, status rigor, variance culture – required to migrate to a connected platform tomorrow.
The value is real: a coherent, auditable loop from offer to invoice in a tool every stakeholder already knows. The limitations are structural: blended-rate costing that masks resource mix, file-based collaboration that caps team size, hard-coded ceilings that force shadow IT, and a VBA dependency that clashes with modern security postures.
For the German Mittelstand firm not yet ready for cloud PPM or Professional Services Automation, the toolchain delivers immediate structure. For the organization planning its next decade, it delivers a clear-eyed view of what Excel can do – and where the platform must eventually give way.