The Spreadsheet That Wanted to Be a Project Manager

The Single-File Ambition

In the world of project management software, the gap between enterprise platforms and a blank spreadsheet is vast. Enterprise tools offer dependency engines, resource leveling, and multi-user collaboration – but they demand licenses, servers, and weeks of configuration. A blank spreadsheet offers freedom but no guardrails. Into this gap steps a macro-enabled workbook published by Dr. Jürgen Fleig through b-wise GmbH: business-wissen_9921901.xlsm. It is not a cloud application. It is a single .xlsm file, designed to run on a local Windows machine with Excel 2016 or later, macros enabled, and Power Query active.

The artifact positions itself as a standalone planning baseline for small-to-medium classical projects – waterfall efforts spanning up to 36 months. Its author characterizes the competition as powerful, cumbersome, and expensive. The workbook’s counter-pitch is structural coherence: scope, schedule, and cost bound together in one file by a system of keys, conditional formatting, and a mandatory cost-certainty classification. It is a sophisticated exercise in spreadsheet engineering, and its innovations are worth studying precisely because they illuminate where the spreadsheet paradigm reaches its ceiling.

A Relational Model Inside a Flat File

The workbook’s backbone is a hierarchical key system propagated across three primary sheets. On the PROJEKTSTRUKTUR sheet (the Work Breakdown Structure), the planner defines phases, work packages, and sub-packages using a three-tier code:

  • PP (Projektphase) – top-level phase identifier
  • AP (Arbeitspaket) – decomposable work unit
  • TAP (Teilarbeitspaket) – granular task level

When the planner enters a key on the TERMINPLAN (Schedule) or PROJEKTKOSTENPLAN (Cost Plan) sheets, lookup logic auto-populates the task name and responsible person. This eliminates the name drift that plagues disconnected Excel plans where WBS titles are manually retyped in budget sheets. A SORTIEREN button on the WBS sheet allows structural reordering after manual numbering – a necessary concession to the lack of a true outlining engine.

Master data lives in structured tables (ListObjects) on the Auswahllisten and KOSTENSÄTZE sheets. Dropdown lists extend automatically when users tab into the last row, leveraging Excel’s native table expansion. It is a clean implementation of relational integrity inside a flat-file environment.

Soft Constraints: Conditional Formatting as Audit Trail

Absent a scheduling engine that can enforce hard constraints, the workbook implements a novel validation layer: cross-sheet conditional formatting that functions as a visual audit trail.

  • Schedule-to-Cost Check: If a resource is assigned in the Cost Plan for a period falling outside the start/end dates defined in the Schedule, the cell highlights red.
  • Cost-to-Schedule Check: If a task has dates in the Schedule but zero cost allocation in the corresponding months, a flag triggers.

This is referential integrity as detection rather than prevention. It acknowledges the spreadsheet reality that users will break consistency and provides a mechanism to see the breaks immediately. The planner notices a red highlight on an internal engineering line: the cost entry extends into March, but the Schedule ends February 28. They correct the schedule or the cost phasing. The workbook does not stop them from saving an inconsistent plan; it makes the inconsistency visible.

The Certainty Column: Risk at the Line Item

The most methodologically significant feature sits in PROJEKTKOSTENPLAN, Column BA. Every cost line must be tagged with one of three certainty classes:

  • Fixed: Contractual, committed, sunk, or legally obligated (a signed purchase order).
  • Variable: Directly proportional to work volume (internal labor hours, material consumption).
  • Optional: Conditional on future decisions, scope changes, or risk triggers (contingency).

This is not a user-defined dropdown but a structural requirement of the data model. It operationalizes the distinction between commitment and exposure at the line-item level. The source notes align this with AACE International Recommended Practice 10S-90 (Cost Engineering Terminology), specifically the separation of base estimate from contingency. By forcing this classification at the point of entry, the tool prevents the common lump-sum contingency anti-pattern where a single percentage is applied to a total, obscuring which specific work packages carry risk.

In practice, a planner setting up a 12-month R&D project might enter three lines for a mechanical prototype sub-package: external machining vendor (Fixed, PO signed), internal engineering hours (Variable, scope may shift), and contingency material buffer (Optional, risk: spec change). Filtering on Certainty Class = Fixed then establishes the committed baseline for a steering committee review.

The Scheduling Vacuum

For all its structural cleverness, the workbook has a fundamental gap: it contains no scheduling engine. The TERMINPLAN sheet is a visualization of a schedule calculated elsewhere – mentally, on paper, or in Microsoft Project.

  • No dependency logic (Finish-to-Start, Start-to-Start links).
  • No critical path calculation (no forward/backward pass, no float).
  • No resource leveling (the tool checks if cost exists during a task window but cannot move tasks to resolve overallocation).
  • Net Days (Column K) is a simple NETWORKDAYS count, not a duration derived from logic.

The Gantt view renders bars and row highlighting, but the dates are manual inputs. For any project with more than 50 tasks or complex logic, the manual maintenance burden becomes prohibitive and error-prone. The workbook’s bidirectional conditional formatting can flag a date-cost mismatch, but it cannot recalculate the schedule when a predecessor slips.

Hard Horizons and Hidden Calendars

The planning window is fixed at 36 months (Columns Q through AZ). Extending it requires inserting columns, updating all conditional formatting ranges, pivot source ranges, and potentially macro logic – a structural modification beyond the typical end-user. Projects exceeding three years, common in infrastructure, aerospace, or drug development, cannot use the tool without surgery.

The holiday calendar (Feiertage sheet) contains pre-calculated German holidays. While users can add company-specific days, the mechanism for non-standard workweeks (four-day weeks, shift calendars, regional holidays for international teams) is undocumented. The Net Days calculation references this holiday range, but whether it uses NETWORKDAYS.INTL for weekend customization or standard NETWORKDAYS is not exposed.

Reporting That Demands Discipline

The reporting layer (REPORT-JAHR, REPORT-MONAT) uses standard PivotTables. This brings familiar power but also familiar fragility:

  • Manual refresh is mandatory. The TABELLE AKTUALISIEREN (Refresh All) button is a critical procedural choke point. If a stakeholder opens the report tabs without refreshing after the planner updated costs, they view stale data. There is no timestamp or last-refreshed indicator on the dashboard sheets.
  • Filter state persistence is absent. Selections (e.g., Partner = External Lab) reset on refresh or reopen.
  • Drill-through creates a new sheet with raw data, breaking the single-file UX.

Cost rate management carries a silent failure mode. The KOSTENSÄTZE table links resources to rates. Missing rates leave the unit column blank with only a generic hint to update. No validation rule prevents saving a cost line with a blank rate, resulting in silent zero-cost calculations unless the conditional formatting catches the zero-vs-schedule mismatch.

The Collaboration Ceiling

The file is a single-user write artifact. Multi-user concurrency is not supported – no shared workbook legacy feature, no co-authoring in .xlsm with macros and Power Query. Version control is manual (v1.0, v1.1 filenames). There is no audit trail, no baseline snapshot feature (save-as is the only baseline), no user-level permissions (edit WBS vs. edit Costs vs. view Report). Regulatory environments (FDA 21 CFR Part 11, ISO 13485) would require external controls.

Deployment constraints further narrow the usable context. Macros and Power Query refresh generally do not execute in Excel Online, SharePoint, or Teams. Mac Excel support for Power Query is limited or absent in older versions; VBA object model differences may break the SORTIEREN button or conditional formatting logic. Locked-down corporate environments often block unsigned macros or disable Power Query data refresh via Group Policy. The tool is restricted to trusted desktop zones, hindering distributed team access.

Agile as Workaround

The author suggests mapping Epics to Phases (PP) and User Stories to Work Packages (AP), using Story Points as a pseudo-resource unit in KOSTENSÄTZE (e.g., €/Story Point). The TERMINPLAN serves only as a coarse release calendar (Sprint 1, Sprint 2). The source explicitly categorizes this as a workaround because the tool lacks sprint mechanics, velocity tracking, or backlog prioritization views. The 36-month column horizon maps poorly to iterative cadences.

What This Tool Teaches Us

Fleig’s workbook is a high-integrity planning artifact masquerading as a lightweight PM system. Its value proposition is not automation – it requires significant manual discipline (date entry, pivot refresh, rate maintenance) – but structural coherence. It forces the planner to bind scope (WBS), time (Schedule), and money (Cost Plan) via keys and certainty tags, preventing the three-versions-of-the-truth syndrome prevalent in ad-hoc Excel folders.

As a case study in spreadsheet-first architecture, it demonstrates how far the grid can be pushed: structured tables for master data, pivot engine for reporting, conditional formatting for cross-sheet validation, VBA glue for sorting and refresh. It also honestly exposes the ceiling where the grid fails: dependency graphs, concurrency, auditability, and scheduling logic.

For the competent individual planner managing a standalone, fixed-scope project in a controlled Windows Excel environment, it is a power tool. For the project organization needing a platform, it is a reminder that some problems require a database, not a spreadsheet.